Smart CI Group were appointed by Equans to deliver a comprehensive HVAC replacement and Building Management System (BMS) upgrade for a live operational facility. Acting as Principal Contractor, we managed the project from initial design through to final handover, successfully completing all works during a complete building shutdown, with no extensions to the deadline.
This project demonstrates our ability to deliver highly technical M&E upgrades within strict timeframes, ensuring full compliance, safety, and system performance across critical building environments such as courtrooms and custody suites.
Completed full HVAC design, including airflow rates, heat gain calculations, services coordination, and equipment selection.
Liaised with Red Engineering, Equans’ incumbent consultant, for design review and approval.
Conducted a valuation survey of existing services to assess the condition and integration requirements.
Supplied and managed scaffolding, including plant hoisting and access/egress for roof-level works.
Provided full site setup, including welfare facilities, security, signage, and waste disposal management.
Removed all existing Air Handling Units (AHUs) and associated ventilation and electrical systems.
Installed four new large Swegon AHUs serving all courts and custody suites, complete with DX air conditioning.
Installed all associated ventilation services, with thermal insulation and air balancing for system efficiency and compliance.
Installed a new plantroom electrical service, including:
BMS panel
AHU and DX air conditioning connections
Local power and lighting supplies
Delivered a full BMS upgrade, providing complete control integration for all new plant.
Supplied and configured a BMS supervisor head end for building-wide system monitoring and management.
Acted as Principal Contractor, submitting the F10 notification and ensuring full CDM compliance.
Provided full-time SMSTS-qualified management throughout the project.
Engaged a third-party health and safety auditor to ensure independent compliance verification.
Conducted final client witnessing, system testing, and submitted complete O&M manuals for handover and certification.
Despite the challenges of a complete building shutdown, Smart CI Group successfully managed all logistics, coordination, and safety requirements to deliver the works on schedule and to specification. Close collaboration with Equans, Red Engineering, and all stakeholders ensured seamless project execution with no disruption to critical post-shutdown operations.
Smart CI Group provided the client with:
Four new high-efficiency Swegon AHU systems with integrated DX air conditioning.
A modern, fully upgraded BMS system providing improved monitoring, control, and energy efficiency.
A safe and compliant installation, completed on time and within the agreed shutdown period.
Comprehensive documentation, testing, and certification for full client assurance.
This project highlights Smart CI Group’s proven capability to deliver complex HVAC and BMS upgrades in time-critical, compliance-driven environments. Our integrated approach ensures:
End-to-end turnkey project delivery – from design and demolition to commissioning and certification.
Principal Contractor management with CDM compliance.
Specialist HVAC and BMS expertise for complex building systems.
Zero downtime delivery within challenging operational constraints.
For more information please feel free to contact us and one of our advisors will be available to help.
Office Opening Hours: 9:00AM – 17:00PM Monday – Friday
Please leave us an email if out of hours.
How can we help?